File #: 18-1041    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 9/17/2018 In control: Board of County Commissioners
On agenda: 10/1/2018 Final action:
Title: Capital Project Amendment No. 19CPA000006 - Appropriate $2,103,200 to Create the Aeration System Improvements Project for the Triangle Wastewater Treatment Plant (TWWTP) SE055 and Award of the Aeration System Improvements for the TWWTP Invitation for Bid (IFB 18-040R1) Contract to English Construction Company, Inc.
Attachments: 1. CPA-06 Supplement Form TWWTP Aeration System Improvements ($2,103,200), 2. CPA-06 Legal Form TWWTP Aeration System Improvements ($2,103,200), 3. MWBE Compliance Review Form, 4. TWWTP Aeration System Improvements
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item:
Title
Capital Project Amendment No. 19CPA000006 - Appropriate $2,103,200 to Create the Aeration System Improvements Project for the Triangle Wastewater Treatment Plant (TWWTP) SE055 and Award of the Aeration System Improvements for the TWWTP Invitation for Bid (IFB 18-040R1) Contract to English Construction Company, Inc.

Body
Date Of BOCC Meeting: October 8, 2018

Request For Board Action:
Agenda Text
The Board is requested to approve Capital Project Amendment No. 19CPA000006 appropriating $2,103,200 to establish the Aeration System Improvements Project for the Triangle Wastewater Treatment Plant (TWWTP) Project SE055. The Board is also requested to award a construction contract to English Construction Company, Inc. in the amount of $1,912,000 for the construction of the Aeration System Improvements and to authorize the County Manager to execute the contract and any related contract amendments, not to exceed a total project budget of $2,103,200.

Project
Aeration System Improvements for the TWWTP (SE055)

Current Budget Totals
$0.00

Increase/Decrease Totals
$2,103,200

Revised Budget Totals
$2,103,200

The Aeration System Improvements for the TWWTP includes the replacement of existing mechanical aeration rotors in oxidation ditch number two with a diffused aeration system consisting of two 125 horsepower blowers with variable frequency drives and two membrane disc diffuser grids. Additional work in oxidation ditch number two includes removing settled solids from the basin, repairing an expansion joint spanning the basin, and replacing all mixers within the basin. A ten percent contingency is recommended for this project to cover unexpected expenses.

Durham County issued an Invitation for Bid (IFB 18-040) on June 7, 2018. IFB 18-040 was advertised in local newspapers and on the Durham County website. Additionally, the requirements were emailed to multiple contractors. Only two bids were received on July 19, 2018. As a result, an additional (IFB 18...

Click here for full text