Item:
Title
Capital Project Amendment No. 21CPA000009 - Increase Snow Hill Road Pump Station and Force Main Replacement Project (DC149) budget by $2.4M in LOBS funding; and authorize the County Manager to execute a design-build contract amendment with Wharton-Smith/Hazen and Sawyer for GMP#2
Body
Date of BOCC Meeting: October 12, 2020
Request for Board Action:
Agenda Text
The Board is requested to approve No. 21CPA000009, increasing the Snow Hill Road Pump Station and Force Main Replacement Project (DC149) budget by $2,400,000 in FY20 LOBS funding; and authorizing the County Manager to execute a design-build contract amendment with Wharton-Smith/Hazen and Sawyer for GMP #2 in the amount of $8,852,879, as well as approve the construction contingency at (3%) in the amount of $265,000 to execute any other related contracts including change orders if necessary not to exceed the available budget of $9,117,879.00 for the design-build Guaranteed Maximum Price #2 for the Snow Hill Road Pump Station and Force Main Project.
The Snow Hill Road Pump Station (SHRPS) was identified as a limiting factor in growth in the Treyburn business district in 2013. Although the SHRPS was upgraded in 2015, the pump station is no longer capable of being upgraded to sufficiently convey wastewater from the Treyburn business district and must be replaced with a larger station and separate force main. Multiple industries within the Treyburn area are in design or construction for expansions of their current facilities; therefore, economic development and job creation will be halted until the SHRPS is complete. On August 26, 2019, the Board approved Capital Project Amendment No. 20CPA000002 in the amount of $12,685,000 as well as the design-build contract execution with Wharton-Smith/Hazen and Sawyer for $1,899,449.90. On May 11, 2020, the Board approved GMP #1 in the amount of $2,965,335.00 to commence construction on early site work.
GMP #2 Contract Package consists of the pump stat...
Click here for full text