Item:
Title
Approval of Capital Project Amendment No.26CPA021 and Budget Ordinance Amendment No.26BCC063 Appropriating $2,561,000.00 of Debt Service Fund Fund Balance to the PAYGO Fund to Create the New Renewable Energy Plan Capital Project (4730DC168) and to Authorize the Execution of Design and Engineering Services Agreement with HDR, Inc for a total not-to-exceed amount of $2,561,000
Body
Date of BOCC Meeting: March 9, 2026
Request for Board Action:
Agenda Text
The Board is requested to approve the Capital Project Amendment No.26CPA021 and Budget Ordinance Amendment No.26BCC063 appropriating $2,561,000 of Debt Service Fund Fund Balance to the PAYGO Fund to create the new Renewable Energy Plan Capital Project (4730DC168), and authorize the County Manager to enter into a contract with HDR, Inc to perform the design and engineering phase for 12 priority facilities for a total not-to-exceed amount of $2,561,000 (see attached proposal).
Project Name and Number
Current Budget
Increase / Decrease
Updated Budget
Renewable Energy Plan Capital Project (4730DC168)
$0.00
$2,561,000.00
$2,561,000.00
TOTAL
$0.00
$2,561,000.00
$2,561,000.00
In February 2022, the Board adopted a Renewable Energy Plan (REP) to reach the goal of running operations on 80% renewable energy by 2030 and 100% by 2050. In order to identify the exact measures needed to implement the plan, in October 2024 the Board approved a contract with HDR, Inc. to conduct Comprehensive Facilities Assessment (CFA) that identified specific, actionable opportunities to increase energy efficiency and convert fossil fuel end-uses to renewable energy. The final CFA report covered 42 of the County's facilities and provided recommendations on energy efficiency retrofits, beneficial electrification of facilities including electric vehicle charging stations, and the incorporation of solar photovoltaics and energy storage as well as financial analysis.
Staff selected 12 of the facilities as priority for...