File #: 26-0358    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 6/22/2026 In control: Board of County Commissioners
On agenda: 8/10/2026 Final action:
Title: Authorize the County Manager to enter into a contract with Ardurra not to exceed $114,800 for construction oversight services for the Whispering Pines Stream Restoration and Stormwater Improvement Project
Attachments: 1. Whispering Pines CACO Services Scope_6-11-2026, 2. Whispering Pines Construction Phase Services - Detailed Task & Fee Breakdown_6-18-2026, 3. Small Business Review Form-Agenda Action Form - RFQ 26-038 Whispering Pines Stream Restoration and Bioretention Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Item:                       

Title

Authorize the County Manager to enter into a contract with Ardurra not to exceed $114,800 for construction oversight services for the Whispering Pines Stream Restoration and Stormwater Improvement Project

 

Body

Date of BOCC Meeting: August 10, 2026

 

Request for Board Action:

Agenda Text

The Board is requested to authorize the County Manager to enter into a contract with Ardurra not to exceed $114,800 for construction oversight services for the Whispering Pines Stream Restoration and Stormwater Improvement Project. 

 

The Whispering Pines Mobile Home Park Stream Restoration Project was identified in the County Stormwater Nutrient Management Strategy as a potential project for compliance with the Falls Lake Nutrient Management Rules.  The project consists of approximately 1,700 linear feet of stream restoration and a bioretention pond to treat stormwater on the property.  The stream restoration project will remove sources of nitrogen and phosphorous from streambank erosion - helping the County meet the nutrient requirements of the Falls Lake Rules - while also reducing flooding impacts to residents of Whispering Pines Mobile Home Park.

 

Ardurra was selected following a qualification-based selection process.  The County has worked with WK Dickson (Ardura) on the design and permitting for the Whispering Pines Project.  WK Dickson was acquired by Ardurra in 2025, and the same team of engineers will continue on the project.

 

The Whispering Pines Project will be funded by a combination of grant funding (+80%) and County Stormwater Utility Fee dollars.

 

Alignment with Strategic Plan: This agenda item supports Strategic Plan Goal 4: Environmental Stewardship and Community Prosperity. More specifically, it supports the objective of improving water quality and reducing flooding hazards to residents.

 

Resource Persons: Ryan D. Eaves, PE, Stormwater and Erosion Control Division Manager; Jay Gibson, PE, Director of Engineering and Environmental Services

 

County Manager’s RecommendationThe County Manager recommends that the Board authorize the County Manager to enter into a contract with Ardurra not to exceed $114,800 for construction oversight services for the Whispering Pines Stream Restoration and Stormwater Improvement Project. 

 

Signature