Legislation Details

File #: 26-0493    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 9/14/2026 In control: Board of County Commissioners
On agenda: 9/28/2026 Final action:
Title: The Board is requested to approve a contract with Brady Trane Services, Inc. in the amount of $201,750.00, for removal of the existing HVAC system and installation of two new 10-ton Trane split systems serving the elevator machine room at the Durham County Courthouse and authorize the County Manager to execute the contract and any necessary change orders or amendments, provided sufficient funds are available within the approved project budget. This project will be funded through the HVAC CIP Program WBS#4190420030076402
Attachments: 1. Scope Durham_County_Courthouse_Elevator_Room_HVAC_Replacement_Option_2_Scope, 2. Elevator Room Split System Replacement Proposal - Option 2 (Roof), 3. AAF Supplemental Document - Courthouse Elevator Room HVAC Replacement Option 2- Brady, 4. Contract Elevator Room Split System Replacement Proposal - Option 2 (Roof)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Item:                       

Title

The Board is requested to approve a contract with Brady Trane Services, Inc. in the amount of $201,750.00, for removal of the existing HVAC system and installation of two new 10-ton Trane split systems serving the elevator machine room at the Durham County Courthouse and authorize the County Manager to execute the contract and any necessary change orders or amendments, provided sufficient funds are available within the approved project budget. This project will be funded through the HVAC CIP Program WBS#4190420030076402

 

Body

Date of BOCC Meeting: September 28, 2026

 

Request for Board Action:

Agenda Text

General Services requests approval of Brady proposal F4-fEDAA0-26-003 through OMNIA Partners Contract 3341. Brady will recover the refrigerant and remove and dispose of the existing HVAC system, then furnish and install two new 10-ton Trane split systems on the 11th-floor balcony on top of the elevator machine room. The work includes refrigerant piping, ductwork, insulation, electrical service, smoke-detector controls, a programmable thermostat, rigging, startup, and inspection. The contract price is $201,750.00, plus applicable North Carolina sales tax. The purchase will use the cooperative purchasing program exemption. The funding will be through HVAC CIP Program WBS#4190420030076402.

 

Alignment with Strategic Plan: This contract aligns with Sustainable Infrastructure and Environment by maintaining and improving the County's built systems. Replacing the courthouse elevator machine-room HVAC system will support reliable elevator operations, improve cooling reliability, and extend equipment service life.

 

Resource Persons: Motiryo Keambiroiro, Director, General Services; Shawn Swiatocha, Assistant Director; Claude Eubanks, Field Superintendent; Dwayne Cofield, Project Facilitator

 

County Manager's Recommendation: The County Manager recommends that the Board authorize the County Manager to execute the proposed contract with Brady Trane Services, Inc. in the amount of $201,75.00, for removal of the existing HVAC system and installation of two new 10-ton Trane split systems serving the elevator machine room at the Durham County Courthouse and authorize the County Manager to execute the contract and any necessary change orders or amendments, provided sufficient funds are available within the approved project budget

 

Signature

County Manager: ____________________________