File #: 24-0688    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 10/23/2024 In control: Board of County Commissioners
On agenda: 11/12/2024 Final action:
Title: Approval of Capital Project Amendment No. 25CPA020 and Budget Ordinance Amendment No.25BCC044 Appropriating $12,349,654 of Sewer Utility Enterprise Fund Fund Balance and Transferring the Funding to the Slater Road Lift Station, Force Main, and Outfall Capital Project (SE066), Transferring $8,303,330 of Budgeted ARPA Funding to the Slater Road Capital Project for a New Total Project Budget of $22,349,654.00; as well as Authorizing the County Manager to Execute a Design-Build Contract Amendment with Crowder Construction Company for the Guaranteed Maximum Price (GMP) in the Amount of $20,052,984.00 and Allowed Construction Contingency of 3% ($600,000) to Execute any Other Related Contracts, Including Change Orders, Not to Exceed the Available Budget of $20,652,984.00 for the Design-Build GMP.
Attachments: 1. _AAF Supplemental Document - GMP Approval - Slater DB Contract_Draft, 2. GMP Summary Estimate (50%) - Slater Road PS 20241023 R1, 3. AAF-44 Legal Form - Sewer Utility for Slater Road ($12,349,654), 4. CPA-20 LEGAL FORM Slater Road ($20,652,984), 5. MWBE Compliance Review Form-AAF RFQ24-026 SLATER ROAD LIFT STATIONS FORCE MAIN AND OUTFALL 110424
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Item:                       

Title

Approval of Capital Project Amendment No. 25CPA020 and Budget Ordinance Amendment No.25BCC044 Appropriating $12,349,654 of Sewer Utility Enterprise Fund Fund Balance and Transferring the Funding to the Slater Road Lift Station, Force Main, and Outfall Capital Project (SE066), Transferring $8,303,330 of Budgeted ARPA Funding to the Slater Road Capital Project for a New Total Project Budget of $22,349,654.00; as well as Authorizing the County Manager to Execute a Design-Build Contract Amendment with Crowder Construction Company for the Guaranteed Maximum Price (GMP) in the Amount of $20,052,984.00 and Allowed Construction Contingency of 3% ($600,000) to Execute any Other Related Contracts, Including Change Orders, Not to Exceed the Available Budget of $20,652,984.00 for the Design-Build GMP.

 

Body

Date of BOCC Meeting: November 12, 2024

 

Request for Board Action:

Agenda Text

The Board is Requested to approve Capital Project Amendment No.25CPA020 and Budget Ordinance Amendment No. 25BCC044 appropriating $12,349,654 of Sewer Utility Enterprise Fund Fund Balance and Transferring the funding to the Slater Road Lift Station, Force Main and Outfall Capital Project (SE066), as well as transferring $8,303,330 of budgeted ARPA funding to the project for a new total project budget of $22,349,654. This amendment also authorizes the County Manager to execute a design-build contract amendment with Crowder Construction Company for the Guaranteed Maximum Price (GMP) in the amount of $20,052,984.00 and allowed construction contingency of 3% ($600,000) to execute any other related contracts, including change orders, not to exceed the available budget of $20,652,984.00 for the design-build GMP.

 

Durham County Capital Projects

Current Budget

Increase/Decrease

Updated Budget

Slater Road Lift Station, Force Main, and Outfall Capital Project (7100SE066)

 $ 1,696,670.00

 $   20,652,984.00

 $ 22,349,654.00

TOTAL

 $ 1,696,670.00

 $   20,652,984.00

 $ 22,349,654.00

A relocated and upgraded Slater Road Lift Station (LS) was recommended in a preliminary engineering report. Upgrades to the LS will increase sewer capacity in the Northeast Creek basin, as well as improve reliability and ease of maintenance.  The Slater Road LS was constructed in 1983. 

Relocation of the Slater Road LS is recommended for the following reasons:

                     The current location lies within Wake County, and customers served in this area can still be served by a gravity system that flows to the relocation point.

                     By moving the LS west of I-540, the force main underneath I-540 can be abandoned, thereby eliminating a potential catastrophic liability.

                     Roughly 1800 feet of existing force main will be abandoned, which will improve pumping efficiency.

                     Construction at the new location allows for the current LS to operate with minimal interruptions or construction conflicts.

 

This project has a delivery method of progressive design-build and involves an ARPA-approved funding of $10M. 

 

DCo Engineering is using the progressive design-build delivery method to expedite project completion and meet ARPA requirements for funds obligation (by December 31, 2024) and funds spent (by December 31, 2026).  The County will be reimbursed for funds spent within ARPA’s eligibility limits (December 31, 2026).

 

This is Phase 2 of the project. Phase 2 consists of the construction of the lift station, force main, and sewer outfall.  Phase I consisted of field evaluations, permitting/encroachment, projecting flows, siting, right-of-way analysis, easement acquisition, surveying, subsurface utility surveys, geotechnical services, detailed design, and development of the Guaranteed Maximum Price (GMP).

 

Alignment with Strategic Plan: This action is in accordance with Durham County’s Forward 2029 Strategic Plan:

                     Proposed Strategic Plan Goal “Sustainable Infrastructure & Environment” by maintaining, protecting, and improving natural and built systems to support a sustainable community.

                     Proposed Strategic Plan Goal “Financial Stewardship” by collecting, funding, and managing resources for high quality service delivery.

 

Resource Persons: Jay Gibson PE, Director of Engineering and Environmental Services; Stephanie Brixey, Deputy Director of Engineering and Environmental Services; Jerry Morrone, Project Manager, Vincent Chirichella, Sr. Project Manager

 

County Manager’s RecommendationThe County Manager recommends that the Board approve Capital Project Amendment No.25CPA020 and Budget Ordinance Amendment No. 25BCC044 appropriating $12,349,654 of Sewer Utility Enterprise Fund Fund Balance and Transferring the funding to the Slater Road Lift Station, Force Main and Outfall Capital Project (SE066), as well as transferring $8,303,330 of budgeted ARPA funding to the project for a new total project budget of $22,349,654. This amendment also authorizes the County Manager to execute a design-build contract amendment with Crowder Construction Company for the Guaranteed Maximum Price (GMP) in the amount of $20,052,984.00 and allowed construction contingency of 3% ($600,000) to execute any other related contracts, including change orders, not to exceed the available budget of $20,652,984.00 for the design-build GMP.

 

Signature

County Manager: ____________________________