Item:
Title
Approval of Capital Project Amendment No.24CPA00023 and Budget Ordinance Amendment No.24BCC00093 Appropriating $350K of Debt Service Fund Balance, Transferring $350K of Debt Service Fund Fund Balance to the PAYGO Fund, and Appropriating $350K from the PAYGO Fund to the Durham County Sheriff’s Training Facility Capital Project (4310DC091) for Preconstruction activities; as well as Execution of a Contract for Preconstruction Services in the Amount of $202,003.00 with CT Wilson Construction Co./Rankin III Grading for the Durham County Sheriff’s Training Facility Project
Body
Date of BOCC Meeting: April 29, 2024
Request for Board Action:
Agenda Text
The Board is requested to approve Capital Project Amendment No.24CPA00023 and Budget Ordinance Amendment No.24BCC00093 appropriating $350K of Debt Service Fund Fund Balance, transferring $350K of Debt Service Fund Fund Balance to the PAYGO Fund, and appropriating $350K of PAYGO funding to the Durham County Sheriff’s Training Facility Capital Project (4310DC091). The Board is also requested to authorize the County Manager to execute a contract with CT Wilson Construction Company and Rankin III Grading for Pre-Construction Services required for the Durham County Sheriff’s Training Facility located at 100 Electra Road, Durham NC, in an amount not to exceed $202,003.00. (See Attachment 1). The balance of transferred funding not used for the pre-construction services contract will be utilized for other required project costs to include site surveying, envelope commissioning services, permit/design fees, site logistics, etc.
|
Project |
Current Budget |
Increase/Decrease |
Revised Budget |
Project Status |
|
Sheriff's Training Facility (4310DC091) |
$ 1,254,608.00 |
$ 350,000.00 |
$ 1,604,608.00 |
Amending |
The Request for Qualifications (RFQ) for Construction Manager at Risk Services for the Durham County Sheriff’s Training Facility was advertised in local newspapers on July 27, 2023. A pre-proposal conference was held on August 8, 2023, and three proposals were received on August 31, 2023. An evaluation committee comprised of representatives from the County Manager’s Office, Durham County Sheriff’s Office, General Services, and Engineering Department reviewed proposals, interviewed all three firms, and found CT Wilson Construction/Rankin III Grading as the most qualified for the project.
The Pre-Construction Services phase of the project is the first step in the Construction Manager at Risk process in which the contracting team will provide cost estimates, constructability reviews, schedule development and value analysis of the project design. This initial contract is necessary for the CM @ R to provide analysis of the schematic design and design development of the project. Funding for this service will be available in the Durham County Sheriff’s Training Facility Capital Project account provided this associated CPA is approved.
This project will entail construction of a new 10,000 square feet training and administrative building, fully renovated outdoor firing range facilities, and site improvements to include improved drainage, walkways, driveways, and parking at the existing Sheriff’s Firing Range. The project is scheduled to receive LEED Silver Certification upon completion. The work will be completed in compliance with the North Carolina Existing Building Code and Durham County's construction standards.
Alignment with Strategic Plan: This aligns with Goal 4 - Environmental Stewardship - through the improvement of an existing facility while repurposing land that is the site of a closed landfill. Goal 5 - Accountable, Efficient, and Visionary Government - by providing consolidated Basic Law Enforcement Training (BLET) services into one facility, providing more efficient training/service delivery.
Resource Persons: Joel T. Jones, Project Manager; James Faress, P.E., Senior Project Manager; Peri D. Manns, Deputy Director of EE&S; David LaBarre, DCSO Director of Planning & Development
County Manager’s Recommendation: The County Manager recommends that the Board approve Capital Project Amendment No.24CPA00023 and Budget Ordinance Amendment No.24BCC00093 appropriating $350K of Debt Service Fund Fund Balance, transferring $350K of Debt Service Fund Fund Balance to the PAYGO Fund, and appropriating $350K of PAYGO funding to the Durham County Sheriff’s Training Facility Capital Project (4310DC091). The Board is also requested to authorize the County Manager to execute a contract with CT Wilson Construction Company and Rankin III Grading for Pre-Construction Services required for the Durham County Sheriff’s Training Facility located at 100 Electra Road, Durham NC, in an amount not to exceed $202,003.00. (See Attachment 1). The balance of transferred funding not used for the pre-construction services contract will be utilized for other required project costs to include site surveying, envelope commissioning services, permit/design fees, site logistics, etc.