Item:
Title
Approval of Capital Project Amendment No.25CPA019 and Budget Ordinance Amendment No. 25BCC043 Appropriating $4,021,221.00 from the Sewer Utility Enterprise Fund Fund Balance and Transferring the Funding to the Page Park Lift Station Capital Project (SE065) for a New Total Project Budget of $4,236,671.00; as well as Authorizing the County Manager to Execute a Design-Build Contract Amendment with Crowder Construction Company for the Guaranteed Maximum Price (GMP) in the Amount of $3,904,221.00 and Allowed Construction Contingency of 3% ($117,000) to Execute Any Other Related Contracts, Including Change Orders, Not to Exceed the Available Budget of $4,021,221.00 for the Design-Build GMP
Body
Date of BOCC Meeting: November 12, 2024
Request for Board Action:
Agenda Text
The Board is requested to approve Capital Project Amendment No.25CPA019 and Budget Ordinance Amendment No. 25BCC043 appropriating $4,021,221 from the Sewer Utility Enterprise Fund Fund Balance and transferring the funding to the Page Park Lift Station Capital Project (SE065) for a new total project budget of $4,236,671.00. This amendment also authorizes the County Manager to execute a Design-Build contract amendment with Crowder Construction Company for the Guaranteed Maximum Price (GMP) in the amount of $3,904,221.00 and allowed construction contingency of 3% ($117,000) to execute any other related contracts, including change orders, not to exceed the available budget of $4,021,221.00 for the Design-Build GMP.
Durham County Capital Projects |
Current Budget |
Increase/Decrease |
Updated Budget |
Page Park Lift Station, Force Main and Outfall Project (SE065) |
$215,450.00 |
$4,021,221.00 |
$4,236,671.00 |
An upgraded Page Park Lift Station (LS) was recommended in a preliminary engineering report. Upgrades to the LS will increase sewer capacity in the Northeast Creek basin, as well as improve reliability and ease of maintenance. The Page Park LS was constructed in 1997.
Upgrade of the Page Park is recommended for the following reasons:
• The current LS is a ‘suction lift’ type; an older technology with components reaching the end of their useful lifecycles.
• Steel components, like bases for pumps, are severely corroded and need replacement.
• The LS will be converted to a submersible LS that is more efficient and requires less maintenance.
• Electrical and instrumentation improvements are needed.
DCo Engineering is using the progressive design-build delivery method to expedite project completion. This is Phase 2 of the project. Phase 2 consists of the construction of the lift station. Phase I consisted of field evaluations, permitting/encroachment, projecting flows, siting, easement acquisition, surveying, subsurface utility surveys, geotechnical services, detailed design, and development of the Guaranteed Maximum Price (GMP).
Alignment with Strategic Plan: This action is in accordance with Durham County’s Forward 2029 Strategic Plan:
• Proposed Strategic Plan Goal “Sustainable Infrastructure & Environment” by maintaining, protecting, and improving natural and built systems to support a sustainable community.
• Proposed Strategic Plan Goal “Financial Stewardship” by collecting, funding, and managing resources for high quality service delivery.
Resource Persons: Jay Gibson PE, Director of Engineering and Environmental Services; Stephanie Brixey, Deputy Director of Engineering and Environmental Services; Jerry Morrone, Project Manager, Vincent Chirichella, Sr. Project Manager
County Manager’s Recommendation: The County Manager recommends that the Board approve Capital Project Amendment No.25CPA019 and Budget Ordinance Amendment No. 25BCC043 appropriating $4,021,221 from the Sewer Utility Enterprise Fund Fund Balance and transferring the funding to the Page Park Lift Station Capital Project (SE065) for a new total project budget of $4,236,671.00. This amendment also authorizes the County Manager to execute a Design-Build contract amendment with Crowder Construction Company for the Guaranteed Maximum Price (GMP) in the amount of $3,904,221.00 and allowed construction contingency of 3% ($117,000) to execute any other related contracts, including change orders, not to exceed the available budget of $4,021,221.00 for the Design-Build GMP.