File #: 24-0753    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 11/19/2024 In control: Board of County Commissioners
On agenda: 12/9/2024 Final action:
Title: Approval of Capital Project Amendment No.25CPA026 Reducing the Detention Center Cell Window Replacement Capital Project (4190DC084) by $500,000 and Increasing the Ongoing Facilities Systems Upgrades Capital Project (4190DC087) by $500,000 to Cover Unanticipated Equipment Replacement Costs
Attachments: 1. AAF Supplemental Document - CIP Budget Amendment, 2. CPA-26 Transfer Window Replacement to Ongoing Maintenance ($0)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item:
Title
Approval of Capital Project Amendment No.25CPA026 Reducing the Detention Center Cell Window Replacement Capital Project (4190DC084) by $500,000 and Increasing the Ongoing Facilities Systems Upgrades Capital Project (4190DC087) by $500,000 to Cover Unanticipated Equipment Replacement Costs

Body
Date of BOCC Meeting: December 9, 2024

Request for Board Action:
Agenda Text
The Board is requested to approve Capital Project Amendment No.25CPA026 reducing the Detention Center Cell Window Replacement Capital Project (4190DC084) by $500,000 and increasing the Ongoing Facilities Systems Upgrades Project (4190DC087) by $500,000 to cover unanticipated equipment replacement costs.

Durham County Capital Projects
Current Budget
Increase/Decrease
Updated Budget
Detention Center Window Replacement (41904200DC084)
$3,060,303.00
($500,000.00)
$2,560,303.00
Ongoing Facilities Systems Project (41904200DC087)
$1,257,070.36
$500,000.00
$1,757,070.36

The Durham County Detention Center fire pump is currently non-functional and needs to be replaced. The Sheriff's staff must conduct round-the-clock fire watch on the building because it does not have a functioning sprinkler system. This condition is a life safety issue for the inmates and staff working at the building. The estimated cost of this project is $300,000.

Also, a bypass line and valves on the domestic water line servicing the Detention Center must be installed. Currently, if the main backflow goes down, there will be no water service to the building. This bypass will allow water service to the building if and when the backflow needs to be repaired. This is a necessary redundancy for a facility that must operate 24-7. The estimated cost of this project is $175,000.

Both projects fall within our Scope for the Ongoing Facilities Systems Upgrades. The Detention Center Window Replacement project's construction cost was well below the estimated project construction cost. This leaves a surplus that can be u...