Approval of Capital Project Amendment No.27CPA018 Reducing Appropriated Funding to Support the New Durham County Emergency Operations Center (EOC) Capital Project (4730DC158) by $5,656,912 for a Revised Total Budget of $49,499,403; and Authorizing the Execution of the Construction Manager At-Risk Guaranteed Maximum Price Contract with Bordeaux Construction for the Construction of the Emergency Operations Center at a Total Amount Not-To-Exceed $38,913,235 (Base Bid, Alternates Plus Owner’s Contingency) Subject to the Review and Approval of the County Attorney's Office
Body
Date of BOCC Meeting: November 9, 2026
Request for Board Action:
Agenda Text
The Board is requested to approve Capital Project Amendment No.27CPA018 reducing appropriated funding to support the New Durham County Emergency Operations Center (EOC) capital project (4730DC158) by $5,656,912 for a revised total budget of $49,499,403, and to authorize the County Manager to enter into a contract with Bordeaux Construction Company for the construction of the Emergency Operations Center at the Guaranteed Maximum Price (GMP) of $37,779,840 (Base Bid, Alternates, Plus Owner’s Contingency) subject to the review and approval of the County Attorney's Office; as well as execute any other related contracts - including change orders if necessary - for a not-to-exceed budget of $38,913,235 (See Attachment 1). Debt issuance and funding determinations will be finalized in the coming months.
Project #
Current Budget
DECREASE
Revised Budget
Emergency Operations Center (4730DC158)
$55,156,315
($5,656,912)
$49,499,403
Summary
$55,156,315
($5,565,912)
$49,499,403
On September 14, 2026, the BOCC appropriated funding and awarded a Construction Manager at Risk (CM@R) contract to Bordeaux Construction in the amount of $45,422,037. This cost included a budgetary not-to-exceed number for the electrical scope of work. Since then, the electrical scope has been refined, yielding ...