Title: Approve Capital Project Amendment No.26CPA013 and Budget Ordinance Amendment No.26BCC044 Appropriating $276,244.80 of Debt Service Fund Fund Balance and Transferring the Funding to the PAYGO Fund to Support the Lincoln Community Health Center Parking Lot Expansion Capital Project (4730DC159); as well as Authorize an Increase in the Owner's Contingency to the contract with WC Construction in the Amount of $276,244.80 to Execute Any Necessary Change Orders for the LCHC Parking Lot Expansion for a Total Not-to-Exceed of $1,333,344.80
Attachments: 1. AAF_Supplemental_Document_LCHC CPA Construction contract AmendmentWC Construction012082025, 2. 251208_Lincoln_Additional Funds Letter - Rev, 3. BCC-44 Legal Form, 4. CPA-13 LEGAL FORM LCHC Parking Lot Exp ($276,244.80)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item:
Title
Approve Capital Project Amendment No.26CPA013 and Budget Ordinance Amendment No.26BCC044 Appropriating $276,244.80 of Debt Service Fund Fund Balance and Transferring the Funding to the PAYGO Fund to Support the Lincoln Community Health Center Parking Lot Expansion Capital Project (4730DC159); as well as Authorize an Increase in the Owner's Contingency to the contract with WC Construction in the Amount of $276,244.80 to Execute Any Necessary Change Orders for the LCHC Parking Lot Expansion for a Total Not-to-Exceed of $1,333,344.80

Body
Date of BOCC Meeting: January 12, 2026

Request for Board Action:
Agenda Text
The Board is requested to approve Capital Project Amendment No.26CPA013 and Budget Ordinance Amendment No.26BCC044 appropriating $276,244.80 of Debt Service Fund Fund Balance and transferring the funding to the PAYGO Fund to support the Lincoln Community Health Center Parking Lot Expansion Capital Project (4730DC159); as well as authorizing an increase to the owners contingency to the contract with WC Construction in the amount of $276,244.80.00, to execute any necessary change orders for the LCHC Parking Lot Expansion for a total Not-to-exceed of $1,333,344.80 (See Attachment 1, Page 1).

Durham County Capital Projects
Current Budget
Increase/Decrease
Updated Budget
Lincoln Community Health Center Parking Lot Expansion Capital Project (4730DC159)
$1,090,600.00
$276,244.80
$1,366,844.80

On March 9, 2020, the Board of County Commissioners created the Lincoln Community Health Center Parking Lot Expansion Project account and authorized the execution of a contract with Surface 678 (S678) to provide Engineering services for this project. The scope of work included demolition of existing lawn area to provide space for construction of an expanded parking lot, minor grading improvements, perimeter fence installation, storm drainage installation, and landscape plantings in and surrounding the parking lot. There are offsite drainage improv...