File #: 25-0476    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 8/19/2025 In control: Board of County Commissioners
On agenda: 9/8/2025 Final action:
Title: Approval of Contract Amendment with Carolina Civilworks, Inc. for Emergency and Scheduled Collection System Repair Services in the Amount of $210,289.02, Bringing the Contract Amount from $400,000 to $610,289.02 and to Execute Any Other Related Contract Amendments Not to Exceed $700,000
Attachments: 1. AAF Supplemental Document, 2. CCW_FR24-626_Contract Pkg, 3. 08.08.25 TW Alexander SS Repair
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item:
Title
Approval of Contract Amendment with Carolina Civilworks, Inc. for Emergency and Scheduled Collection System Repair Services in the Amount of $210,289.02, Bringing the Contract Amount from $400,000 to $610,289.02 and to Execute Any Other Related Contract Amendments Not to Exceed $700,000

Body
Date of BOCC Meeting: September 8, 2025

Request for Board Action:
Agenda Text
The Board is requested to authorize the County Manager to enter into a contract amendment to increase the existing service contract with Carolina Civilworks, Inc. (FR# 24-626 and RFP# 21-022) for emergency and scheduled collection system repairs in the amount of $210,289.02, bringing the total contract amount from $400,000 to $610,289.02, and to execute any other related contracts, including amendments, not to exceed $700,000.

The Utilities Division maintains approximately 112 miles of gravity sanitary sewer pipes, 10 miles of force main, 3,112 manholes, and 13 lift stations. Per the Collection System Permit, WQCS00038, the County is required to repair areas of concern as needed to ensure there are no sanitary system overflows (SSOs). A contract was put in place with Carolina Civilworks, Inc. for emergency and scheduled collection system repairs that include repairs to collection system equipment, piping and sewer lateral repair and installation. Emergency repairs frequently happen after hours, holidays, and during inclement weather.

This contract is funded from the Enterprise Fund's operating budget.

Alignment with Strategic Plan: This action is in accordance with Durham County Strategic Goal: "Sustainable Infrastructure & Environment," as this aids in the prevention of sanitary sewer overflows (SSOs) and/or lessens the impact to the environment. No additional policy impacts are expected.

Resource Persons: Jay Gibson PE, Director of E&ES; Vince Chirichella PE, Sr. Project Manager; Stephanie Brixey, Deputy Director of E&ES

County Manager's Recommendation: The Count...