Item:
Title
Authorization to Amend the Design Contract with RND Architects, PA for Design Development and Construction Administration Services for the Stanford L. Warren Interior Upgrades Project in the Amount of $14,470 for a Total Revised Contract Amount of $242,669.
Body
Date of BOCC Meeting: October 13, 2025
Request for Board Action:
Agenda Text
The Board is requested to authorize the County Manager to execute a contract amendment with RND Architects, PA in the amount of $14,470 for a total revised contract amount of $242,669 for extended architectural and engineering design services required to address water intrusion discovered at the northern stair tower of Stanford L. Warren Library.
As interior renovations at SL Warren Library were wrapping up, pooling water was discovered in the lower level of the north stair tower after the Hurricane Helene rain event. RND Architects was tasked with conducting an investigation to determine the source, which was traced back to failing water proofing membrane applied during the 2004 addition/renovation to the library. With this discovery, RND Architects was then asked to provide a design solution and extended construction administrative services required for the repairs that were beyond the original scope of the project.
Funding for this fee amendment is available within the existing capital project account for the Stanford L. Warren Library envelope repairs.
Alignment with Strategic Plan: This item aligns with Safe and Resilient Community Goal, Objective SR 2- Create happy, healthy, and safe places for residents and County employees; as well as the Sustainable Infrastructure and Environment Goal, Objective SI3- Preserve and restore the natural and built environment.
Resource Persons: Joel T. Jones, Project Manager; James Faress, Senior Project Manager; Peri Manns, Deputy Director; Engineering and Environmental Services; Jay Gibson, P.E., Director of Engineering and Environmental Services; Charles Nic...