File #: 26-0244    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 5/4/2026 In control: Board of County Commissioners
On agenda: 5/11/2026 Final action:
Title: Approval of Contract Amendment with J&A Engineering, LLC. in the Amount of $7,440 for New Total of $152,960 for Security Engineering Design and Construction Administration at the Durham County Jail
Attachments: 1. J&A Sup, 2. J&A_Contract Amendment Template_FY2026, 3. Durham Detention Center Security Engineering Add Services Proposal 041426
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Item:                       

Title

Approval of Contract Amendment with J&A Engineering, LLC. in the Amount of $7,440 for New Total of $152,960 for Security Engineering Design and Construction Administration at the Durham County Jail

 

Body

Date of BOCC Meeting: May 11, 2026

 

Request for Board Action:

Agenda Text

The Board is requested to authorize the County Manager to execute a contract amendment with J&A Engineering, LLC. in the amount of $7,440 for new total of $152,960 for security engineering design and construction administration at the Durham County Jail. Funding for this amendment currently exists within the Detention Security Upgrade Project.

 

New low voltage requirements will incorporate digital signage systems at the intake and public waiting areas including access control and video intercom systems at public entry.

 

Alignment with Strategic Plan: This item aligns with the County’s Strategic Plan: Goal #3 Safe Community

 

Resource PersonsDavid LaBarre, Director of Planning & Development, Durham County Sheriff’s Office; Justin Ellerbe, Chief of Detention Services, Durham County Sheriff’s Office; Clarence Birkhead, Sheriff of Durham County. 

 

County Manager’s RecommendationThe County Manager recommends that the Board authorize the County Manager to execute a contract amendment with J&A Engineering, LLC. in the amount of $7,440 for new total of $152,960 for security engineering design and construction administration at the Durham County Jail. Funding for this amendment currently exists within the Detention Security Upgrade Project.

 