File #: 24-0314    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 5/21/2024 In control: Board of County Commissioners
On agenda: 5/28/2024 Final action:
Title: Approval of Capital Project Amendment No.24CPA00027 and Budget Ordinance Amendment No.24BCC00103 Appropriating $215,450 of Sewer Utility Enterprise Fund Fund Balance and Transferring Those Funds to the New Page Park Lift Station, Force Main, and Outfalls Capital Project (7100SE065); Approval of a Contract with the Design-Build Firm Crowder Construction Company to Provide Pre-Construction Services in the Amount of $205,191; and Authorize the County Manager to Execute the Contract and Any Related Contract Amendments not to exceed $215,450.
Attachments: 1. _AAF Supplemental Document - Contract Approval - Page Pk DB Contract_Final Draft, 2. _240501 FINAL Draft_DBIA 535-GCs for Page_Pk, 3. _240501 FINAL Draft_DBIA 545-Prog-D-B-Agreement Page_Pk, 4. _240520 Page Pk_Rd_PS_DBIA_EXHIBIT A Owners Project Criteria, 5. _240520 Page Pk_Rd_PS_DBIA_EXHIBIT B Scope of Phase I Services, 6. _240520 Page Pk_Rd_PS_DBIA_EXHIBIT C Insurance Requirements, 7. 240502 County Attorney Approval, 8. _240520 Durham County - Page Park Lift Station Phase 1 MWBE Fee Summary, 9. 240503 MWBE Compliance Review Form-AAF for 24-026R1 RFQ, 10. AAF-103 and CPA-27 LEGAL FORM Appropriating $215,450 in Sewer Utility Fund FB, 11. CPA-27 & BCC-103 LEGAL FORM Appropriating ARPA and Sewer Utility Funds for new Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item:
Title
Approval of Capital Project Amendment No.24CPA00027 and Budget Ordinance Amendment No.24BCC00103 Appropriating $215,450 of Sewer Utility Enterprise Fund Fund Balance and Transferring Those Funds to the New Page Park Lift Station, Force Main, and Outfalls Capital Project (7100SE065); Approval of a Contract with the Design-Build Firm Crowder Construction Company to Provide Pre-Construction Services in the Amount of $205,191; and Authorize the County Manager to Execute the Contract and Any Related Contract Amendments not to exceed $215,450.

Body
Date of BOCC Meeting: May 28, 2024

Request for Board Action:
Agenda Text
The Board is requested to approve Capital Project Amendment No.24CPA00027 and Budget Ordinance Amendment No.24BCC00103 appropriating $215,450.00 of Sewer Utility Enterprise Fund Fund Balance and transferring those funds to the new Page Park Lift Station, Force Main and Outfalls Capital Project (7100SE065); approving a contract with the design-build firm Crowder Construction Company to provide pre-construction services in the amount of $205,191; and authorizing the County Manager to execute the contract and any related contract amendments not-to-exceed $215,450.

Project
Current Budget
Increase
Revised Budget
Page Park Apartment Lift Station (7100SE065)
$ -
$ 215,450.00
$ 215,450.00
TOTAL
$ -
$ 215,450.00
$ 215,450.00

An upgraded Page Park Lift Station (LS) was recommended in a preliminary engineering report. Upgrades to the LS will increase sewer capacity in the Northeast Creek basin, as well as improve reliability and ease of maintenance. The Page Park LS was constructed in 1997.
Upgrade of the Page Park is recommended for the following reasons:
* The current LS is a 'suction lift' type; an older technology with components reaching the end of their useful lifecycles.
* Steel components, like bases for pumps, are severely corroded and nee...

Click here for full text