File #: 19-0046    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 1/17/2019 In control: Board of County Commissioners
On agenda: 2/11/2019 Final action:
Title: Capital Project Amendment No. 19CPA000012- Moving 2016 General Obligation Bond Funds Between Multiple Durham Public School Capital Projects and Closing Five Bond Funded Capital Projects
Attachments: 1. CPA-12 Legal Form for Closing and Moving GO Bond Funds Between DPS Capital Projects
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Item:                       

Title

Capital Project Amendment No. 19CPA000012- Moving 2016 General Obligation Bond Funds Between Multiple Durham Public School Capital Projects and Closing Five Bond Funded Capital Projects

 

Body

Date Of BOCC Meeting:  February 11, 2019

 

Request For Board Action:

Agenda Text

On January 10, 2019, the Durham Public Schools (DPS) Board of Education approved adjustments to multiple 2016 Bond funded Capital Projects. Pursuant to the Interlocal Agreement with DPS, as amended, the Durham County Board of County Commissioners is requested to consider and approve the closing of five DPS Capital Projects and moving funds between multiple Capital Projects. The projects that DPS closed as part of this transfer are SH244 (Middle School Gym Renovations), SH259 (Parkwood Roof Replacement), SH260 (Spaulding Roof Replacement), SH263 (Fuller Building Roof Replacement), and SH270 (Lighting Upgrades).

 

These projects are not officially closed yet in the County’s asset management system.  Any project that has had activity during the fiscal year cannot be closed in the asset management system until the next fiscal year.  The County will bring another amendment to BOCC in FY2019-20 to officially close these projects in the County’s asset management system.

 

The table below indicates funds reconciled by DPS and the County that are available for transfer:

 

Project

Current Budget

Increase/ Decrease

Revised Budget

Project Status

16 GO Bond - Middle School Gym Renovations (SH244)

$457,315.30

$0.00

$457,315.30

Closing

16 GO Bond -School for Creative Studies Renovations (SH251)

$369,177.92

$142,289.02

$511,466.94

Amending

16 GO Bond -Harris Roof Replacement (SH256)

$808,391.87

($19,250.00)

$789,141.87

Amending

16 GO Bond -Parkwood Roof Replacement (SH259)

$250,000.00

($53,859.40)

$196,140.60

Closing

16 GO Bond -Spaulding Roof Replacement (SH260)

$425,000.00

($39,791.02)

$385,208.98

Closing

16 GO Bond -Fuller Building Roof Replacement (SH263)

$262,500.00

($17,759.02)

$244,740.98

Closing

16 GO Bond -Lighting Upgrades (SH270)

$1,453,606.00

($11,629.58)

$1,441,976.42

Closing

 

 

 

 

 

Totals

$4,025,991.09

$0.00

$4,025,991.09

 

 

Alignment With Strategic Plan: This capital project amendment aligns with Goal 1-Community and Family Prosperity and Enrichment, though providing access to educational, vocational, economic and cultural opportunities and by providing support for educational opportunities that ensure high academic achievement.

 

 

Resource PersonsAaron Beaulieu, Chief Operating Officer, Construction & Capital Planning.

 

County Manager’s Recommendation: The County Manager recommends that the Board approve Capital Project Amendment No. 19CPA000012 closing five Capital Projects and moving 2016 General Obligation (GO) Bond funds between other Capital Projects.

 

Signature

County Manager: ____________________________