File #: 19-0131    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 3/14/2019 In control: Board of County Commissioners
On agenda: 4/8/2019 Final action:
Title: Capital Project Amendment No. 19CPA000015- Moving 2016 General Obligation Bond Funds Between Multiple Durham Public School Capital Projects and Closing Two Bond Funded Capital Projects
Attachments: 1. CPA-15 Legal Form Moving 2016 General Obligation Bond Funds Between Multiple DPS Capital Projects and Closing Two Bond Funded Capital Projects
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Item:                       

Title

Capital Project Amendment No. 19CPA000015- Moving 2016 General Obligation Bond Funds Between Multiple Durham Public School Capital Projects and Closing Two Bond Funded Capital Projects

 

Body

Date of BOCC Meeting:  April 8, 2019

 

Request for Board Action:

Agenda Text

On March 14, 2019, the Durham Public Schools (DPS) Board of Education approved adjustments to multiple 2016 Bond funded Capital Projects. Pursuant to the Interlocal Agreement with DPS, as amended, the Durham County Board of County Commissioners is requested to consider and approve the closing of two DPS Capital Projects and moving funds between multiple Capital Projects. The projects that DPS closed as part of this transfer are SH245 (Rogers Herr Fire Alarm Replacement) and SH254 (Club Blvd. Roof Replacement).

 

These projects are not officially closed yet in the County’s asset management system.  Any project that has had activity during the fiscal year cannot be closed in the asset management system until the next fiscal year.  The County will bring another amendment to BOCC in FY2019-20 to officially close these projects in the County’s asset management system.

 

The table below indicates funds reconciled by DPS and the County that are available for transfer:

 

Project                                                                                                                                                    Current       Inc./Dec.        Revised         Project                     

Budget                                                           Budget          Status

16 GO Bond - Club Blvd. Roof Replacement  (SH254)                     $875,000    ($40,628.89)   $834,371.11    Closing

16 GO Bond - Rogers Herr Fire Alarm Replacement (SH245)                     $187,500    ($13,425.55)   $174,067.45    Closing

16 GO Bond - Staff Development Roof Replacement (SH265)                     $312,500     $48,000.00     $360,500.00   Amending

16 GO Bond - Existing Northern High School (SH249)                     $250,000     $6,061.44       $256,061.44   Amending

 

Totals                                                                                                                                                   $1,625,000       $0.00          $1,625,000

 

Alignment with Strategic Plan: This capital project amendment aligns with Goal 1-Community and Family Prosperity and Enrichment, though providing access to educational, vocational, economic and cultural opportunities and by providing support for educational opportunities that ensure high academic achievement.

 

Resource PersonsFred Jernigan, Senior Project Manager, Construction & Capital Planning.

 

County Manager’s Recommendation: The County Manager recommends that the Board approve Capital Project Amendment No. 19CPA000015 closing two Capital Projects and moving 2016 General Obligation (GO) Bond funds between other Capital Projects.

 

Signature

County Manager: ____________________________