File #: 19-0561    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 11/7/2019 In control: Board of County Commissioners
On agenda: 12/9/2019 Final action:
Title: Execution of the Amendment to the Architectural Design Service Contract with O'Brien/Atkins Associates, P.A. for the Detention Center Security Modifications Project No. DC008
Attachments: 1. Attachment 1 - OBA additional services amendment 11-2019.pdf, 2. AAF - Supplemental Document Form - Detention Center Staff Entrance Officers' Station - Architectural Services Contract Amendment 2.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item:
Title
Execution of the Amendment to the Architectural Design Service Contract with O'Brien/Atkins Associates, P.A. for the Detention Center Security Modifications Project No. DC008

Body
Date of BOCC Meeting: December 9, 2019

Request for Board Action:
Agenda Text
The Board is requested to authorize the County Manager to amend the Contract for Architectural Design Services with O'Brien/Atkins Associates, P.A. of Durham, to provide additional architectural services for Security Modifications to the Durham County Detention Center located at 219 South Mangum Street, Durham, in the amount of $21,560.00 thus totaling a not to exceed amount of $278,898.00 (See Attachment 1, pages 1 &2.)

Funds for the Architectural Design Services for this project were approved by the BOCC in January 2017. The project to replace the officers' stations was advertised for Bids in July of 2018 with C.T. Wilson Construction Co. submitting the low bid. Before work began on this project, the Board of County Commissioners requested that safety improvements be made to the detainee's beds and the HVAC grilles within the Detention Center housing units. The Officers' Station project was delayed in order to allow the work of both projects to occur simultaneously in each housing unit. The Contractor mobilized at the Detention Center to conduct the work of both projects in February 2019 after required construction materials had been ordered and received, thereby further minimizing disruptions to the Sheriff's Department operations. This coordinated dual project effort extended the contract completion date for the Officers' Station project by four months and the completion date for the concurrent projects became February 16, 2020.

We are requesting a fee increase of $21,560 that includes four additional months of construction administration services that are necessary to accommodate the revised project completion date of February 2020.

Alignment with Strategic Plan: This aligns wi...

Click here for full text