Title: Black & Veatch Efficiency and Resiliency Improvements Project Contract Amendment
Attachments: 1. AAF Supplemental Documnet 11.04.pdf, 2. Signed Original Contract, 3. Amendment #1, 4. Amendment #2, 5. Amendment #3, 6. Amendment #4, 7. Amendment #5, 8. Amendment #6, 9. Amendment #7, 10. MWBE Compliance Review Form - AAF, 11. Scope & Fee Letter for Sodium Hypochlorite Chemical Feed System Improvements, 12. Scope & Fee Letter for Aeration System Improvements
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Item:                       

Title

Black & Veatch Efficiency and Resiliency Improvements Project Contract Amendment

 

Body

Date of BOCC Meeting:  November 12, 2019

 

Request for Board Action:

Agenda Text

The Board is requested to authorize the County Manager to enter into a contract amendment to increase the existing design consultant contract with Black & Veatch International Company (FR# 17-832) for the Efficiency and Resiliency Improvements Project (RFQ 17-012) in the amount of $41,500, bringing the total contract amount from $471,400 to $512,900, and to execute any other related contracts, including amendments, not to exceed $560,000.

 

Alignment with Strategic Plan: This action is in accordance with Durham County Strategic Plan Goal 4: “Environmental Stewardship and Community Prosperity”.

 

Resource PersonsJay Gibson PE, General Manager; Peri Manns ASLA, Interim General Manager; Stephanie Brixey, Deputy Director of Engineering and Environmental Services; Vince Chirichella PE, Senior Project Manager 

 

County Manager’s RecommendationThe County Manager recommends the Board to authorize the County Manager to enter into a contract amendment to increase the existing design consultant contract with Black & Veatch International Company (FR# 17-832) for the Efficiency and Resiliency Improvements Project (RFQ 17-012) in the amount of $41,500, bringing the total contract amount from $471,400 to $512,900, and to execute any other related contracts, including amendments, not to exceed $560,000.

 