File #: 19-0195    Version: 1 Name:
Type: Action Item Status: Consent Agenda
File created: 4/15/2019 In control: Board of County Commissioners
On agenda: 4/22/2019 Final action:
Title: Execution of the Contract Amendment with Skanska Holt Brothers (Construction Manager @ Risk) for the Audio Visual Contract for the Main Library Renovation Project. (Project No.: DC094)
Attachments: 1. AAF CMAR Amendment backups, 2. AAF - MWBE attachment 2, 3. AAF_Supplemental_Document_CMAR_AV_Contract_Amendment_Main_Library
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Item:
Title
Execution of the Contract Amendment with Skanska Holt Brothers (Construction Manager @ Risk) for the Audio Visual Contract for the Main Library Renovation Project. (Project No.: DC094)
Body
Date of BOCC Meeting: April 22, 2019

Request for Board Action:
Agenda Text
The Board is requested to authorize the County Manager to amend the CM@R contract with Skanska Holt Brothers (SHB) to include a contract with Whitlock (W) for the audiovisual system installation at the Durham County Main Library (DCML) building located at 300 N. Roxboro St. Durham, North Carolina in the amount of $671,986.00 (Base Bid plus alternates 1,2,3,4,and 7c), thus increasing the construction expenses to $39,887,605.00, plus previously approved contingencies in the amount of $1,176,469.00 thus totaling a not to exceed budget of $41,064,074.00. Funding for this amendment is available in the Capital Project account.

On June 12, 2017 & December 12, 2017 the BOCC awarded the CMAR GMP Packages 1 & 2 respectively to Skanska Holt Brothers. Typically, the County would bid the AV package but the decision was made to allow the CMAR to bid this package therefore managing this work under their contract for project continuity. The request for proposals (RFP) for the audiovisual system was advertised on February 15, 2019 and a Pre-Bid Conference was on February 19, 2019 at 3:00 P.M. Three (3) responses were received on March 5, 2019. The bids were reviewed along with the scope of work for the installation were evaluated by Skanska Holt Brothers and certified by Vines Architecture. Whitlock was deemed the most qualified firm for the project and submitted the lowest base price for this service in the amount of $627,668.00 (base bid only). Funding for this contract is available in the Capital Project account. (See Attachment 1, Page 1 - 3).

Whitlock will supply audiovisual equipment, audiovisual furniture, labor, installation, materials, programming, testing, training, and follow-up su...

Click here for full text